Following the CSI MasterFormat, which divisions contain project submittal requirements for a fire protection system?

Prepare for the Special Hazards Systems Level 2 Test with an interactive quiz. Use flashcards and multiple-choice questions with hints and explanations to enhance your learning experience. Achieve readiness for your certification exam with ease!

Multiple Choice

Following the CSI MasterFormat, which divisions contain project submittal requirements for a fire protection system?

Explanation:
Divisions 01 General Requirements and Division 21 Fire Suppression contain project submittal requirements for a fire protection system. Division 01 covers the general submittal process that applies to all trades, while Division 21 includes the fire protection-specific submittals such as sprinkler drawings, product data, installation details, and hydraulic calculations. The other divisions listed do not govern the fire protection submittal content. This combination ensures both the overall submittal workflow and the system-specific documentation are addressed.

Divisions 01 General Requirements and Division 21 Fire Suppression contain project submittal requirements for a fire protection system. Division 01 covers the general submittal process that applies to all trades, while Division 21 includes the fire protection-specific submittals such as sprinkler drawings, product data, installation details, and hydraulic calculations. The other divisions listed do not govern the fire protection submittal content. This combination ensures both the overall submittal workflow and the system-specific documentation are addressed.